The cost estimates for the Macquarie Point stadium and its broader precinct released by the Tasmanian Government today put the price of the stadium build at $1.23 billion, while other works in the precinct and project delivery costs have been identified as $132 million and $183 million respectively.
The most recently release previous project budget for the stadium was $1.13 billion, while costs released in late May 2025 put the stadium build at $945 million.
The state government said higher costs were being driven by the war in Iran, high oil prices, increased costs for materials, high labour costs and the complexity of the project.
“Major projects are always challenging, but as a state we must be able to say yes to opportunity, new industry and economic growth,” said Tasmania’s premier, Jeremy Rockliff.
“Every generation gets a handful of opportunities to shape the future, and the stadium is one of those opportunities.
“We know this project has the potential to unlock hundreds of millions of private investment, and we are already seeing the benefits.
“This is about the jobs created, the skills developed, the confidence built and the opportunities unlocked for generations to come.”
The stadium will deliver Hobart’s largest business events space, with an indoor event space with capacity to host 1,500 people part of the venue.
Business Events Tasmania CEO, Marnie Craig, spoke publicly on Monday and made a statement to micenet today about the benefits of the new stadium.
“For Tasmania’s business events industry, Macquarie Point represents a generational opportunity,” said Craig.
“This isn’t simply a stadium project; it is a multipurpose precinct that has had conferencing, exhibitions and business events embedded at the core of its design.
“Business Events Tasmania has worked closely with the Macquarie Point Development Corporation at every step to ensure the facilities are fit-for-purpose and meet the needs of future event organisers and delegates.
“The demand is tangible. We have already had 10 national associations enquire about bringing future conferences collectively worth $45 million to Tasmania and Macquarie Point, including events that have historically been turned away due to capacity.
“Together with investments in event infrastructure across the north and south of the state, Macquarie Point will mark a step change in our event hosting capability, increasing capacity from 1,100 delegates to 1,500 and opening the door to a new calibre of national and international business events.”
“As we look towards welcoming scaled events from 2031, Tasmania’s business events industry stands on the cusp of an exciting era of growth and opportunity,” said Craig.